Venting Requirements for Poly Tanks
| Mechanical Pump Fill | Pneumatic Fill | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| IF ≤ 1,000 gallons | IF – Vent length ≤ 3′ | IF – Vent length > 3′ and ≤ 30′ | IF – Scrubber or fume tight application | ||||||
| ✔ Vent size should equal size of largest fill or discharge fitting | ✔ Maintain vent screen mesh size ≥ 1/4″ or no screen used | ✔ 3 or less 90º elbows with no other restrictions or reduction in pipe size | ✔ Vent pipe size throughout scrubber system CANNOT be reduced! | ||||||
| ✔ Centerline of dispersion pipe not to be submersed > 6″ | |||||||||
| IF > 1,000 gallons | ✔ Emergency Pressure Relief Cover Required IF > 1,000 gallons | ✔ Emergency Pressure Relief Cover Required IF > 1,000 gallons | ✔ Perforated dispersion pipe must be same diameter as vent or larger. Sum of perforations ≥ cross-sectional area of pipe | ||||||
| ✔ Vent size should exceed the largest fill or discharge fitting by 1″ | |||||||||
| Tanker Discharge | Inlet/ Fitting Size | Min Vent Size | Tanker Discharge | Inlet/ Fitting Size | Min Vent Size | Tanker Discharge | Inlet/ Fitting Size | Min Vent Size | |
| 2″ | 2″ | 4″ | 2″ | 2″ | 6″ | 2″ | 2″ | 6″ | |
| 3″ | 2″ | 6″ | 3″ | 2″ | 6″ | 3″ | 2″ | 8″ | |
| 3″ | 3″ | 6″ | 3″ | 3″ | 8″ | 3″ | 3″ | 10″ | |
Click to see guidelines for vent placement.
Venting charts based on recommendation and criteria from Venting Design for ACFM Technical Paper.